United States › Grid › Interconnection queues › Connecticut

SOLAR · ISO-NE

Fusion Solar Center

Fusion Solar Center is a 20.0 MW solar request built and operating in the ISO-NE interconnection queue, in New London County, Connecticut, connecting to NU.

Queue statusOperating
  1. PlanningQueued Feb 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Apr 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
715
Grid region
ISO-NE (New England)
Utility / transmission owner
NU
Connection point (POI)
Eversource Tunnel 12S
Location
New London County, Connecticut
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
21 February 2018
Proposed online date
April 2018

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem