🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 300 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2024 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1486
Grid region
ISO-NE (New England)
Connection point (POI)
Bunker Hill 115kV substation
Location
New Haven County, Connecticut
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
2 January 2024
Proposed online date
June 2027
Withdrawn
January 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem