πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

GAS Β· ISO-NE

Towantic Energy

Towantic Energy is a 452 MW gas request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2007 (completed)
  2. Withdrawn / abandonedJan 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
207
Grid region
ISO-NE (New England)
Connection point (POI)
CL&P 115 kV lines between Baldwin Junction and Bea
Location
New Haven County, Connecticut
Technology
Gas: 452 MW Β· Oil
Total requested
452 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
3 April 2007
Proposed online date
December 2014
Withdrawn
January 2012

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem