United States › Grid › Interconnection queues › Massachusetts
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 315 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Essex County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2022 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1252
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Ward Hill 345 kV Substation
- Location
- Essex County, Massachusetts
- Technology
- Battery: 315 MW
- Total requested
- 315 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress
- Queue status
- Withdrawn
- Entered queue
- 21 April 2022
- Proposed online date
- August 2032
- Withdrawn
- December 2025
Location
Marker shows the centre of Essex County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Essex County
- Battery StorageBattery storage · 225 MW · in study
- Battery StorageBattery storage · 200 MW · in study
- Footprint Combined Cycle UnitGas · 716 MW · built
- Simple Cycle Gas TurbineGas · 61.9 MW · built
- Gas Turbine IncreaseGas · 10.9 MW · built
- Salem Harbor Station IncreaseOther · 8.0 MW · built
- Covanta Haverhill Landfill GasOther · 1.6 MW · built
- Simple CycleGas · 478 MW · withdrawn
- Battery StorageBattery storage · 241 MW · withdrawn
- Battery StorageBattery storage · 150 MW · withdrawn
- Peabody PowerGas · 97.2 MW · withdrawn
- NG NEMA Group DER StudyBattery storage · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem