Covanta Haverhill Landfill Gas

Covanta Haverhill Landfill Gas is a 1.6 MW other request built and operating in the ISO-NE interconnection queue, in Essex County, Massachusetts.

Queue statusOperating
  1. PlanningQueued Dec 2006 (completed)
  2. ConsentedFeb 2023 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
189
Grid region
ISO-NE (New England)
Connection point (POI)
NGRID 23 kV circuit # 2371 from Ward Hill substati
Location
Essex County, Massachusetts
Technology
Other: 1.6 MW
Total requested
1.6 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
15 December 2006
Agreement signed
27 February 2023
Proposed online date
December 2007

Location

Marker shows the centre of Essex County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Essex County