OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2023 requests) — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,249298.6 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,249 requests · page 17 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar Star Frontier BESS
Battery storage · Solar Star Frontier BESS, LLC
101 MWIn study Cameron, TXERCOT Jun 2023target 2029
Long Point Solar II
Solar
101 MWPaused / redesign Brazoria, TXERCOT Jan 2023target 2025
Hide Town Energy Storage
Battery storage · Hide Town Energy Storage LLC
101 MWIn study Scurry, TXERCOT Jan 2023target 2028
Lupinus Solar 3
Solar + storage · Lupinus Solar 2, LLC
101 MWAgreement signed Franklin, TXERCOT Sep 2023target 2026
Rutile BESS
Battery storage · Rutile BESS, LLC
101 MWAgreement signed Runnels, TXERCOT Jan 2023target 2028
Echols Creek Storage
Other · BT Ferguson Solar, LLC
101 MWPaused / redesign Lamar, TXERCOT Apr 2023target 2027
Lemma Solar
Solar · Greening USA Corp.
101 MWIn study Knox, TXERCOT Apr 2023target 2028
Felix Storage
Solar + storage · Felix 1, LLC
101 MWIn study Wilbarger, TXERCOT Jan 2023target 2027
Timber Cove Solar SLF
Solar + storage · Freestone Solar, LLC
101 MWIn study Freestone, TXERCOT May 2023target 2027
Mud Cat Solar SLF
Solar + storage · Mud Cat Solar, LLC
101 MWIn study Lamar, TXERCOT Oct 2023target 2027
Timberline Storage
Solar + storage · Timberline Renewables, LLC
101 MWIn study Nacogdoches, TXERCOT Aug 2023target 2029
Wizard Ranch Solar
Solar
101 MWPaused / redesign Jack, TXERCOT May 2023
Lazy Frog Solar SLF
Solar + storage · Lazy Frog Solar, LLC
100 MWIn study Franklin, TXERCOT Sep 2023target 2028
Goldfinch Storage
Solar + storage · BT DJ4M Solar, LLC
100 MWIn study Van Zandt, TXERCOT Oct 2023target 2028
Firebird Solar
Solar
100 MWPaused / redesign Ector, TXERCOT Nov 2023target 2026
Pledgor BESS
Battery storage · Pledgor BESS
100 MWIn study Matagorda, TXERCOT May 2023target 2028
Rogers Creek BESS
Battery storage · Dialville BESS
100 MWIn study Cherokee, TXERCOT May 2023target 2028
Battery storage project G0922, Cowlitz County
Battery storage
100 MWIn study Cowlitz, WAWest Sep 2023target 2026
Battery storage project AI2-114, Augusta County
Battery storage
100 MWIn study Augusta, VAPJM Mar 2023target 2029
Battery storage project 723, Canyon County
Battery storage
100 MWIn study Canyon, IDWest Jun 2023target 2027
Solar project AI2-036, Augusta County
Solar
100 MWIn study Augusta, VAPJM Jan 2023target 2027
Onshore wind project G0867, Sherman County
Onshore wind
100 MWIn study Sherman, ORWest Jun 2023target 2027
Solar + storage project 2023-G4, Butte County
Solar + storage
100 MWIn study Butte, CAWest Aug 2023target 2028
Solar + storage project GI-2023-171, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Apr 2023target 2026
Battery storage project GEN-2023-055, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Oct 2023target 2028
Solar + storage project 732, Baker County
Solar + storage · MN8 Energy Development Company LLC
100 MWAgreement signed Baker, ORWest Aug 2023target 2029
Battery storage project IC-1116, Carroll County
Battery storage
100 MWAgreement signed Carroll, GASoutheast Jan 2023target 2027
Solar
Solar
100 MWIn study Rockingham, NHISO-NE Jul 2023target 2028
Solar project 919393, Wake County
Solar · Duke Energy Progress, LLC
100 MWIn study Wake, NCSoutheast Sep 2023
Battery storage project GEN-2022-154, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Feb 2023target 2027
Battery storage project AJ1-019, Southampton County
Battery storage
100 MWIn study Southampton, VAPJM Jun 2023target 2028
Solar + storage project 719, Blaine County
Solar + storage · Moonstone Energy 2, LLC
100 MWAgreement signed Blaine, IDWest Jun 2023target 2028
Solar + storage project GEN-2023-104, Woods County
Solar + storage
100 MWIn study Woods, OKSPP Oct 2023target 2028
Other project 6, Chelan County
Other
100 MWIn study Chelan, WAWest Oct 2023target 2027
Battery storage project AJ1-003, Mecklenburg County
Battery storage
100 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Battery storage project 327, Citrus County
Battery storage · Duke Energy Florida, LLC
100 MWUnder construction Citrus, FLSoutheast May 2023target 2027
Battery storage project AJ1-002, Rockingham County
Battery storage
100 MWIn study Rockingham, VAPJM Apr 2023target 2028
Battery storage project GEN-2022-156, Creek County
Battery storage
100 MWIn study Creek, OKSPP Feb 2023target 2027
Battery storage project AJ1-016, Cambria County
Battery storage
100 MWIn study Cambria, PAPJM Jun 2023target 2028
Onshore wind project GEN-2023-173, Kearny County
Onshore wind
100 MWIn study Kearny, KSSPP Oct 2023target 2029
Solar + storage project 165, Pima County
Solar + storage
100 MWIn study Pima, AZWest Sep 2023target 2028
Solar project AI2-328, Madison County
Solar
100 MWIn study Madison, OHPJM Mar 2023target 2026
Battery storage project 3RSC-2023-02, Pueblo County
Battery storage
100 MWIn study Pueblo, COWest May 2023target 2025
Battery storage project GI-2023-166, Imperial County
Battery storage
100 MWIn study Imperial, CAWest Jan 2023target 2024
Solar + storage project Q493, Pinal County
Solar + storage
100 MWIn study Pinal, AZWest Feb 2023target 2025
Solar project J1916, Branch County
Solar
100 MWIn study Branch, MIMISO Oct 2023target 2026
Battery storage project GEN-2022-102, Clay County
Battery storage
100 MWIn study Clay, MOSPP Jan 2023target 2027
Blue Summit Energy Storage
Wind + storage · NextEra Energy Interconnection Holdings, LLC
100 MWAgreement signed Wilbarger, TXERCOT Oct 2023target 2026
Battery storage project 724, Canyon County
Battery storage
100 MWIn study Canyon, IDWest Jun 2023target 2027
Battery storage project 547, Roane County
Battery storage
100 MWIn study Roane, TNSoutheast Apr 2023target 2026
Page 17 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)