United States › Grid › Interconnection queues › Georgia
BATTERY STORAGE · SOUTHEASTBattery storage project IC-1116, Carroll County
Battery storage project IC-1116, Carroll County is a 100 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Carroll County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Jan 2023 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1116
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Roopville DS Substation 230 kV Bus
- Location
- Carroll County, Georgia
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 31 January 2023
- Proposed online date
- August 2027
Location
Marker shows the centre of Carroll County; the queue data does not give exact sites.
Other requests in Carroll County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem