🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Missouri

BATTERY STORAGE · SPP

Battery storage project GEN-2022-102, Clay County

Battery storage project GEN-2022-102, Clay County is a 100 MW battery storage request in interconnection study in the SPP interconnection queue, in Clay County, Missouri, connecting to KCPL.

Queue statusIn planning
  1. PlanningQueued Jan 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-102
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Liberty West 161 kV
Location
Clay County, Missouri
Technology
Battery: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
6 January 2023
Proposed online date
January 2027

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Clay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem