🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Goldfinch Storage

Goldfinch Storage is a 100 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Van Zandt County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0254
Grid region
ERCOT (Texas)
Developer
BT DJ4M Solar, LLC
Connection point (POI)
Tap Connection Bus 2485 Poetry Switch – 3223 Shamburger Switch
Location
Van Zandt County, Texas
Technology
Battery: 100 MW · Battery
Total requested
100 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
4 October 2023
Proposed online date
March 2028

Location

Marker shows the centre of Van Zandt County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Van Zandt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem