Goldfinch Solar

Goldfinch Solar is a 151 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Van Zandt County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0253
Grid region
ERCOT (Texas)
Developer
BT DJ4M Solar, LLC
Connection point (POI)
Tap Connection Bus 2485 Poetry Switch – 3223 Shamburger Switch
Location
Van Zandt County, Texas
Technology
Solar: 151 MW · Battery
Total requested
151 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 September 2023
Proposed online date
June 2028

Location

Marker shows the centre of Van Zandt County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Van Zandt County