United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTRogers Creek BESS
Rogers Creek BESS is a 100 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Cherokee County, Texas.
Queue statusIn planning
- PlanningQueued May 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0414
- Grid region
- ERCOT (Texas)
- Developer
- Dialville BESS
- Connection point (POI)
- Tap 138 KV DailVille (3160) - Neches Pump (3296)
- Location
- Cherokee County, Texas
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 15 May 2023
- Proposed online date
- April 2028
Location
Marker shows the centre of Cherokee County; the queue data does not give exact sites.
Other requests in Cherokee County
- Lumberjack StorageBattery storage · 50.9 MW · agreement signed
- Eagle Pines GasGas · 1,174 MW · in study
- Gas project J480, Cherokee CountyGas · 1,240 MW · withdrawn
- Ponta Power PlantGas · 484 MW · withdrawn
- Ponta Power StationGas · 459 MW · withdrawn
- Solar project GEN-2024-155, Cherokee CountySolar · 200 MW · withdrawn
- AltajacGas · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem