BATTERY STORAGE · ERCOT

Solar Star Frontier BESS

Solar Star Frontier BESS is a 101 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0181
Grid region
ERCOT (Texas)
Developer
Solar Star Frontier BESS, LLC
Connection point (POI)
8656 Luna 138kV
Location
Cameron County, Texas
Technology
Battery: 101 MW
Total requested
101 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
28 June 2023
Proposed online date
February 2029

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cameron County