πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Long Point Solar II

Long Point Solar II is a 101 MW solar request suspended in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Jan 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0390
Grid region
ERCOT (Texas)
Location
Brazoria County, Texas
Technology
Solar: 101 MW
Total requested
101 MW
Queue status
Suspended
Entered queue
16 January 2023
Proposed online date
December 2025

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem