United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in MISO (Midcontinent) (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project J116, Hancock County Onshore wind |
999 MW | Withdrawn / abandoned |
| Gas project J167, Dakota County Gas |
500 MW | Withdrawn / abandoned |
| Onshore wind project J115, St. Francois County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project J154, Washington County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project H041, Lincoln County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J151, Moody County Onshore wind |
350 MW | Withdrawn / abandoned |
| Gas project J129, Polk County Gas |
300 MW | Withdrawn / abandoned |
| Gas project J130, Hancock County Gas |
300 MW | Withdrawn / abandoned |
| Onshore wind project G925, Dewitt County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project J131, Lyon County Gas |
300 MW | Withdrawn / abandoned |
| Gas project J162, Dallas County Gas |
270 MW | Withdrawn / abandoned |
| Onshore wind project G935, Clinton County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project G865, Benton County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project G871, Freeborn County Onshore wind |
201 MW | Withdrawn / abandoned |
| Nuclear project J123, Goodhue County Nuclear |
200 MW | Withdrawn / abandoned |
| Onshore wind project J176, Gratiot County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J133, Codington County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J170, Tuscola County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J168, Dekalb County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project H003, Mcdonough County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G670, Faribault County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J189, Minnehaha County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J187, Shiawassee County Onshore wind |
198 MW | Withdrawn / abandoned |
| Gas project J073, Blue Earth County Gas |
194 MW | Withdrawn / abandoned |
| Onshore wind project J156, Marshall County Onshore wind |
186 MW | Withdrawn / abandoned |
| Onshore wind project J134, Dane County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J182, Dodge County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J114, Tama County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J158, Piatt County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J111, Mower County Onshore wind |
150 MW | Withdrawn / abandoned |
| Gas project J120, Butler County Gas |
135 MW | Withdrawn / abandoned |
| Onshore wind project G742, Missaukee County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project J159, Macon County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J160, Macon County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J113, Atchison County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J190, Ottawa County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J185, Huron County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J184, Rock County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J128, Marshall County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J121, Ford County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J186, Huron County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J163, Tippecanoe County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J178, Burleigh County Onshore wind |
99.6 MW | Withdrawn / abandoned |
| Onshore wind project J150, Mountrail County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J146, Fond Du Lac County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J166, Fulton County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J188, Lenawee County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J164, Erie County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J165, Fulton County Onshore wind |
97.6 MW | Withdrawn / abandoned |
| Onshore wind project J177, St. Croix County Onshore wind |
97.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 Β· 22.6 GW
- PJM (Mid-Atlantic, Midwest)361 Β· 21.6 GW
- CAISO (California)168 Β· 19.1 GW
- Southeast (non-ISO utilities)18 Β· 11.1 GW
- MISO (Midcontinent)72 Β· 10.9 GW
- SPP (Southwest Power Pool)50 Β· 9,058 MW
- ERCOT (Texas)28 Β· 3,689 MW
- ISO-NE (New England)12 Β· 1,337 MW
- NYISO (New York)5 Β· 1,285 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)