United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J185, Huron County

Onshore wind project J185, Huron County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Huron County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2010 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. ConsentedMay 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J185
Grid region
MISO (Midcontinent)
Connection point (POI)
Bauer - Rapson 345 kV
Location
Huron County, Michigan
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
15 November 2010
Agreement signed
29 May 2013
Proposed online date
September 2011
Withdrawn
May 2013

Location

Marker shows the centre of Huron County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Huron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem