ONSHORE WIND Β· MISO

Onshore wind project J166, Fulton County

Onshore wind project J166, Fulton County is a 99.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Fulton County, Ohio.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedMay 2011 (project stopped here)
  3. ConsentedMay 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J166
Grid region
MISO (Midcontinent)
Connection point (POI)
FE Allen Junction Substation 138kV
Location
Fulton County, Ohio
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
10 September 2010
Agreement signed
20 May 2011
Proposed online date
December 2010
Withdrawn
May 2011

Location

Marker shows the centre of Fulton County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Fulton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem