BATTERY STORAGE Β· PJM

Battery storage project AG2-054, Fulton County

Battery storage project AG2-054, Fulton County is a 100 MW battery storage request withdrawn in the PJM interconnection queue, in Fulton County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-054
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Developer
Orchid Acres Solar Project, LLC
Connection point (POI)
Fulton 138 kV
Location
Fulton County, Ohio
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
2 December 2020
Proposed online date
September 2024
Withdrawn
July 2025

Location

Marker shows the centre of Fulton County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Fulton County