ONSHORE WIND Β· MISO

Onshore wind project J188, Lenawee County

Onshore wind project J188, Lenawee County is a 99.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Lenawee County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J188
Grid region
MISO (Midcontinent)
Connection point (POI)
Moore Rd - Beecher 138 kV line
Location
Lenawee County, Michigan
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
7 December 2010
Agreement signed
10 July 2012
Proposed online date
September 2013
Withdrawn
July 2012

Location

Marker shows the centre of Lenawee County; the queue data does not give exact sites.