ONSHORE WIND Β· MISO

Onshore wind project J128, Marshall County

Onshore wind project J128, Marshall County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Marshall County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2010 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J128
Grid region
MISO (Midcontinent)
Connection point (POI)
Oglesby - El Paso 138kV
Location
Marshall County, Illinois
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
26 April 2010
Agreement signed
28 August 2012
Proposed online date
June 2011
Withdrawn
August 2012

Location

Marker shows the centre of Marshall County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Marshall County