ONSHORE WIND Β· MISOOnshore wind project J265, Marshall County
Onshore wind project J265, Marshall County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Marshall County, Illinois.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2012 (completed)
- Withdrawn / abandonedJun 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J265
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 3 miles SE of Toluca, IL
- Location
- Marshall County, Illinois
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 19 November 2012
- Withdrawn
- June 2015
Location
Marker shows the centre of Marshall County; the queue data does not give exact sites.
Other requests in Marshall County
- Onshore wind project J2247, Marshall CountyOnshore wind Β· 178 MW Β· in study
- Solar project J3188, Marshall CountySolar Β· 35.0 MW Β· in study
- Onshore wind project J715, Marshall CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project AF2-003, Marshall CountyOnshore wind Β· 303 MW Β· withdrawn
- Onshore wind project J128, Marshall CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project Y3-035, Marshall CountyOnshore wind Β· 97.5 MW Β· withdrawn
- Onshore wind project Q85, Marshall CountyOnshore wind Β· 20.0 MW Β· withdrawn