ONSHORE WIND · MISO

Onshore wind project J2247, Marshall County

Onshore wind project J2247, Marshall County is a 178 MW onshore wind request in interconnection study in the MISO interconnection queue, in Marshall County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2247
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Woodhall
Location
Marshall County, Illinois
Technology
Wind: 178 MW
Total requested
178 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
25 March 2022
Proposed online date
September 2024

Location

Marker shows the centre of Marshall County; the queue data does not give exact sites.