United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J190, Ottawa County

Onshore wind project J190, Ottawa County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Ottawa County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J190
Grid region
MISO (Midcontinent)
Connection point (POI)
Kenowa 345kV Substation
Location
Ottawa County, Michigan
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
21 December 2010
Proposed online date
July 2019
Withdrawn
July 2017

Location

Marker shows the centre of Ottawa County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Ottawa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem