United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· MISOSolar project J1556, Ottawa County
Solar project J1556, Ottawa County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Ottawa County, Michigan, connecting to METC.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedFeb 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1556
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Northern Fibre 138kV
- Location
- Ottawa County, Michigan
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 23 June 2020
- Proposed online date
- September 2023
- Withdrawn
- February 2021
Location
Marker shows the centre of Ottawa County; the queue data does not give exact sites.
Other requests in Ottawa County
- Solar project J1663, Ottawa CountySolar Β· 200 MW Β· under construction
- Replacing 749 MW of coal generation with BESS; Campbell 3Other Β· 749 MW Β· in study
- Gas project J4159, Ottawa CountyGas Β· 664 MW Β· in study
- Gas project J4160, Ottawa CountyGas Β· 425 MW Β· in study
- Battery storage project J2499, Ottawa CountyBattery storage Β· 100 MW Β· in study
- Battery storage project J1880, Ottawa CountyBattery storage Β· 60.0 MW Β· in study
- Battery storage project J1984, Ottawa CountyBattery storage Β· 50.0 MW Β· in study
- Coal project G479, Ottawa CountyCoal Β· 29.0 MW Β· built
- Battery storage project J3258, Ottawa CountyBattery storage Β· 200 MW Β· withdrawn
- Battery storage project J3320, Ottawa CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project J1527, Ottawa CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project J931, Ottawa CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem