United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project J146, Fond Du Lac County

Onshore wind project J146, Fond Du Lac County is a 99.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Fond Du Lac County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandonedMay 2011 (project stopped here)
  3. ConsentedMay 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J146
Grid region
MISO (Midcontinent)
Connection point (POI)
ATC Green Lake - N. Fond du Lac 138 kV
Location
Fond Du Lac County, Wisconsin
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
28 June 2010
Agreement signed
13 May 2011
Proposed online date
March 2012
Withdrawn
May 2011

Location

Marker shows the centre of Fond Du Lac County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Fond Du Lac County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem