United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· MISOOnshore wind project G925, Dewitt County
Onshore wind project G925, Dewitt County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Dewitt County, Illinois.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2010 (completed)
- Withdrawn / abandonedOct 2012 (project stopped here)
- ConsentedOct 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G925
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Clinton - Brokaw 345kV
- Location
- Dewitt County, Illinois
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 12 May 2010
- Agreement signed
- 8 October 2012
- Proposed online date
- October 2010
- Withdrawn
- October 2012
Location
Marker shows the centre of Dewitt County; the queue data does not give exact sites.
Other requests in Dewitt County
- Solar project J1840, Dewitt CountySolar Β· 250 MW Β· in study
- Solar project J4158, Dewitt CountySolar Β· 100 MW Β· in study
- Solar + storage project AH1-541, Dewitt CountySolar + storage Β· 92.4 MW Β· in study
- Nuclear project J4010, Dewitt CountyNuclear Β· 21.0 MW Β· in study
- Alta Farms IIOnshore wind Β· 197 MW Β· built
- Onshore wind project U4-037, Dewitt CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J273, Dewitt CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project J474, Dewitt CountyOnshore wind Β· 144 MW Β· withdrawn
- Battery storage project J3358, Dewitt CountyBattery storage Β· 100 MW Β· withdrawn
- Onshore wind project J1080, Dewitt CountyOnshore wind Β· 99.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem