ONSHORE WIND Β· MISO

Onshore wind project J474, Dewitt County

Onshore wind project J474, Dewitt County is a 144 MW onshore wind request withdrawn in the MISO interconnection queue, in Dewitt County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2015 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. ConsentedOct 2018 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J474
Grid region
MISO (Midcontinent)
Connection point (POI)
New 138 kV Tabor substation
Location
Dewitt County, Illinois
Technology
Wind: 144 MW
Total requested
144 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
14 September 2015
Agreement signed
25 October 2018
Proposed online date
October 2017
Withdrawn
July 2021

Location

Marker shows the centre of Dewitt County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Dewitt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem