ONSHORE WIND Β· MISO

Onshore wind project J151, Moody County

Onshore wind project J151, Moody County is a 350 MW onshore wind request withdrawn in the MISO interconnection queue, in Moody County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandonedDec 2012 (project stopped here)
  3. ConsentedDec 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J151
Grid region
MISO (Midcontinent)
Connection point (POI)
Split Rock Substation
Location
Moody County, South Dakota
Technology
Wind: 350 MW
Total requested
350 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
28 June 2010
Agreement signed
27 December 2012
Proposed online date
May 2011
Withdrawn
December 2012

Location

Marker shows the centre of Moody County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Moody County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem