United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J170, Tuscola County

Onshore wind project J170, Tuscola County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Tuscola County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J170
Grid region
MISO (Midcontinent)
Connection point (POI)
Karn - Manning 138kV
Location
Tuscola County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
14 September 2010
Agreement signed
18 July 2012
Proposed online date
September 2011
Withdrawn
July 2012

Location

Marker shows the centre of Tuscola County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Tuscola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem