ONSHORE WIND Β· MISO

Onshore wind project G742, Missaukee County

Onshore wind project G742, Missaukee County is a 120 MW onshore wind request withdrawn in the MISO interconnection queue, in Missaukee County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandonedSep 2011 (project stopped here)
  3. ConsentedSep 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G742
Grid region
MISO (Midcontinent)
Connection point (POI)
METC Wexford - Keystone 138kV
Location
Missaukee County, Michigan
Technology
Wind: 120 MW
Total requested
120 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
17 June 2010
Agreement signed
14 September 2011
Proposed online date
October 2009
Withdrawn
September 2011

Location

Marker shows the centre of Missaukee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Missaukee County