United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project G743, Missaukee County

Onshore wind project G743, Missaukee County is a 45.0 MW onshore wind request built and operating in the MISO interconnection queue, in Missaukee County, Michigan.

Queue statusOperating
  1. PlanningQueued Feb 2007 (completed)
  2. ConsentedMar 2010 (completed)
  3. Construction (completed)
  4. OperatingDec 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G743
Grid region
MISO (Midcontinent)
Connection point (POI)
WPSC Cadillac - Leroy 69kV
Location
Missaukee County, Michigan
Technology
Wind: 45.0 MW
Total requested
45.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
16 February 2007
Agreement signed
26 March 2010
Proposed online date
December 2009
Came online
December 2009

Location

Marker shows the centre of Missaukee County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Missaukee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem