United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project J182, Dodge County

Onshore wind project J182, Dodge County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Dodge County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2010 (completed)
  2. Withdrawn / abandonedJun 2013 (project stopped here)
  3. ConsentedJun 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J182
Grid region
MISO (Midcontinent)
Connection point (POI)
Pleasant Valley Substation
Location
Dodge County, Minnesota
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
15 November 2010
Agreement signed
26 June 2013
Withdrawn
June 2013

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Dodge County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem