United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J554, Dodge County

Solar project J554, Dodge County is a 1.0 MW solar request built and operating in the MISO interconnection queue, in Dodge County, Minnesota.

Queue statusOperating
  1. PlanningQueued Mar 2016 (completed)
  2. ConsentedMar 2017 (completed)
  3. Construction (completed)
  4. OperatingOct 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J554
Grid region
MISO (Midcontinent)
Connection point (POI)
Kasson - Dodge Center 69 kV
Location
Dodge County, Minnesota
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
28 March 2016
Agreement signed
6 March 2017
Proposed online date
October 2016
Came online
October 2016

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Dodge County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem