United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project J441, Dodge County
Onshore wind project J441, Dodge County is a 170 MW onshore wind request withdrawn in the MISO interconnection queue, in Dodge County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2015 (completed)
- Withdrawn / abandonedAug 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J441
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Byron 345 kV Substation
- Location
- Dodge County, Minnesota
- Technology
- Wind: 170 MW
- Total requested
- 170 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 15 April 2015
- Proposed online date
- September 2019
- Withdrawn
- August 2019
Location
Marker shows the centre of Dodge County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Dodge County
- Onshore wind project G242, Dodge CountyOnshore wind Β· 19.0 MW Β· built
- Onshore wind project G171, Dodge CountyOnshore wind Β· 14.0 MW Β· built
- Solar project J554, Dodge CountySolar Β· 1.0 MW Β· built
- Onshore wind project G882, Dodge CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Onshore wind project G852, Dodge CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G796, Dodge CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G779, Dodge CountyOnshore wind Β· 260 MW Β· withdrawn
- Onshore wind project J310, Dodge CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J182, Dodge CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project G239, Dodge CountyOnshore wind Β· 63.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem