ONSHORE WIND Β· MISO

Onshore wind project J176, Gratiot County

Onshore wind project J176, Gratiot County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Gratiot County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2010 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J176
Grid region
MISO (Midcontinent)
Connection point (POI)
METC Nelson - Goss 345kV
Location
Gratiot County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
15 November 2010
Agreement signed
20 August 2012
Withdrawn
August 2012

Location

Marker shows the centre of Gratiot County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Gratiot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem