πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project J177, St. Croix County

Onshore wind project J177, St. Croix County is a 97.5 MW onshore wind request withdrawn in the MISO interconnection queue, in St. Croix County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2010 (completed)
  2. Withdrawn / abandonedSep 2013 (project stopped here)
  3. ConsentedSep 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J177
Grid region
MISO (Midcontinent)
Connection point (POI)
Pine Lake - Apple River 161kV
Location
St. Croix County, Wisconsin
Technology
Wind: 97.5 MW
Total requested
97.5 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
15 November 2010
Agreement signed
9 September 2013
Proposed online date
July 2015
Withdrawn
September 2013

Location

Marker shows the centre of St. Croix County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in St. Croix County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem