United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J926, St. Croix County

Solar project J926, St. Croix County is a 101 MW solar request under construction in the MISO interconnection queue, in St. Croix County, Wisconsin, connecting to NORTHERN STATES POWER COMPANY.

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedJun 2021 (completed)
  3. Construction (current stage)
  4. OperatingTarget Sep 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J926
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Pine Lake - Apple River 161 kV Line
Location
St. Croix County, Wisconsin
Technology
Solar: 101 MW
Total requested
101 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
3 June 2021
Proposed online date
September 2023

Location

Marker shows the centre of St. Croix County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in St. Croix County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem