ONSHORE WIND Β· MISOOnshore wind project J158, Piatt County
Onshore wind project J158, Piatt County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Piatt County, Illinois.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandonedSep 2013 (project stopped here)
- ConsentedSep 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J158
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Ameren Brokaw - Champaign 138kV
- Location
- Piatt County, Illinois
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 19 August 2010
- Agreement signed
- 9 September 2013
- Proposed online date
- September 2012
- Withdrawn
- September 2013
Location
Marker shows the centre of Piatt County; the queue data does not give exact sites.
Other requests in Piatt County
- Onshore wind project J1360, Piatt CountyOnshore wind Β· 300 MW Β· agreement signed
- Solar project J3382, Piatt CountySolar Β· 171 MW Β· in study
- Other project IP12, Piatt CountyOther Β· 500 MW Β· withdrawn
- Onshore wind project J1021, Piatt CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J1118, Piatt CountyOnshore wind Β· 150 MW Β· withdrawn