United States βΊ Grid βΊ Interconnection queues βΊ Missouri
ONSHORE WIND Β· MISOOnshore wind project J168, Dekalb County
Onshore wind project J168, Dekalb County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Dekalb County, Missouri.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2010 (completed)
- Withdrawn / abandonedApr 2011 (project stopped here)
- ConsentedApr 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J168
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Ameren Excelsior Springs Substation
- Location
- Dekalb County, Missouri
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 13 September 2010
- Agreement signed
- 21 April 2011
- Proposed online date
- December 2010
- Withdrawn
- April 2011
Location
Marker shows the centre of Dekalb County; the queue data does not give exact sites.
Other requests in Dekalb County
- Onshore wind project GEN-2015-005, Dekalb CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project GI-51, Dekalb CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2016-088, Dekalb CountyOnshore wind Β· 151 MW Β· withdrawn
- Onshore wind project GEN-2016-040, Dekalb CountyOnshore wind Β· 18.4 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem