OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in ERCOT (Texas)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,158262.0 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,158 requests · page 1 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Comanche Peak 3 and 4
Nuclear · TXU Generation
3,200 MWWithdrawn / abandoned ERCOT Sep 2006target 2021
Victoria City Nuclear
Nuclear · Exelon Generation Company, LLC
3,200 MWWithdrawn / abandoned ERCOT Nov 2007target 2050
Bay City Nuclear Station
Nuclear · Exelon Power Team
3,200 MWWithdrawn / abandoned ERCOT Oct 2006target 2050
Shell Windenergy - Briscoe
Onshore wind · Shell Windenergy, Inc. & Luminant
2,940 MWWithdrawn / abandoned ERCOT Oct 2007target 2013
STP 3 and 4
Nuclear · STP Nuclear Operating Company
2,700 MWWithdrawn / abandoned ERCOT Dec 2006
Cobisa-Greenville
Battery storage · Cobisa
2,023 MWWithdrawn / abandoned ERCOT Jul 2002target 2017
Grimes County Energy
Gas · Invenergy
1,280 MWWithdrawn / abandoned ERCOT Mar 2008
Corner Solar
Solar · Shannon Solar LLC
1,222 MWWithdrawn / abandoned Crockett, TXERCOT Jun 2019target 2021
Navarrro-LS
Gas · Pin Oak Creek Energy, LLC
1,200 MWWithdrawn / abandoned ERCOT Sep 2007target 2050
Fannin
Gas · Pattillo Branch Power Company, LLC
1,200 MWWithdrawn / abandoned ERCOT Jun 2007target 2050
White Stallion Energy Center
Coal · White Stallion Energy Center, LLC
1,200 MWWithdrawn / abandoned ERCOT Sep 2008target 2050
CottonWood
Gas · Cottonwood Energy Company LP
1,160 MWWithdrawn / abandoned ERCOT Nov 2005
Rockwood G
Gas · Lincoln Clean
1,122 MWWithdrawn / abandoned ERCOT Apr 2014target 2019
Floyd County
Onshore wind · BP Wind Energy North America, Inc
1,100 MWWithdrawn / abandoned ERCOT Jun 2007target 2050
Perseus Gas
Gas · Engie Flexible Generation NA LLC
1,057 MWWithdrawn / abandoned ERCOT Aug 2024target 2028
Paluxy Solar
Solar · S&S Renewables LLC
1,029 MWWithdrawn / abandoned ERCOT Jan 2023target 2027
B&B Panhandle Wind
Onshore wind · B&B Panhandle Wind,LLC
1,001 MWWithdrawn / abandoned ERCOT Feb 2007target 2050
Hardeman Windfarm
Onshore wind · FPL Energy, LLC
1,000 MWWithdrawn / abandoned ERCOT Jun 2008
R-Cube Wind
Onshore wind · Nextera
1,000 MWWithdrawn / abandoned Denton, TXERCOT Aug 2018target 2020
Mesa Power Project
Onshore wind · Mesa Power Pampa, LLC
1,000 MWWithdrawn / abandoned ERCOT Aug 2007target 2050
Shawnee G
Gas · Lincoln Clean
928 MWWithdrawn / abandoned ERCOT Jul 2014target 2019
Pondera King G
Gas · CPV
925 MWWithdrawn / abandoned ERCOT Sep 2007target 2017
SPC Jackson G
Gas · Southern Power Company
916 MWWithdrawn / abandoned ERCOT Jan 2013target 2018
Limestone 3
Coal · NRG Energy, Inc
875 MWWithdrawn / abandoned ERCOT Aug 2007target 2050
Cotton Energy Center
Gas · FPL Energy, LLC
875 MWWithdrawn / abandoned ERCOT Dec 2007target 2050
Brownsville G
Gas · Tenaska
871 MWWithdrawn / abandoned ERCOT Jul 2012target 2020
Tradinghouse 4
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Tradinghouse 3
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Valley 4
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Morgan Creek 7
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Monticello 4
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Big Brown 3
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Lake Creek 3
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Martin Lake 4
Coal · TXU Power
858 MWWithdrawn / abandoned ERCOT May 2006target 2050
Eagle Mountain SES
Gas · Luminant
853 MWWithdrawn / abandoned ERCOT Jul 2014target 2019
Tenaska Trailblazers
Coal · Tenaska Trailblazers Partners, LLC
850 MWWithdrawn / abandoned ERCOT Feb 2008target 2019
Wolf Hollow II, LP
Gas · Stark Investments
810 MWWithdrawn / abandoned ERCOT Nov 2007target 2050
Sandy Creek 2
Coal · LS Power Associated LP
800 MWWithdrawn / abandoned ERCOT Apr 2006target 2050
Site C Brazos G
Gas · Brazos Elec Coop
800 MWWithdrawn / abandoned ERCOT Apr 2014target 2021
Pinecrest G
Gas · Coronado Ventures
785 MWWithdrawn / abandoned ERCOT Oct 2012target 2020
Navarro Energy Ctr. II
Gas · Summit Navarro, LLC
775 MWWithdrawn / abandoned ERCOT Dec 2007target 2050
Rolling Oak 2
Onshore wind · Airtricity, Inc
750 MWWithdrawn / abandoned ERCOT Mar 2007target 2050
Mesa Power Project
Coal · Mesa Power Pampa, LLC
750 MWWithdrawn / abandoned ERCOT Aug 2007target 2050
Grandview (Last) W
Onshore wind · Eon
750 MWWithdrawn / abandoned ERCOT Mar 2009target 2018
FGE Texas 1 Gas
Gas · FGE Power
743 MWWithdrawn / abandoned Mitchell, TXERCOT Apr 2013target 2021
Oilton Wind Farm
Onshore wind · American Shoreline, Inc
734 MWWithdrawn / abandoned ERCOT May 2008
LaPaloma G
Gas · Coronado Ventures
730 MWWithdrawn / abandoned ERCOT May 2012target 2019
Greens Bayou 9 CCGT
Gas · NRG Texas Power LLC
721 MWWithdrawn / abandoned Harris, TXERCOT target 2025
Tehuacana Creek Solar-Alt POI
Solar · Tehuacana Creek Solar LLC
715 MWWithdrawn / abandoned Freestone, TXERCOT Oct 2022target 2025
Hollow Branch Creek Solar SLF
Solar · Hollow Branch Creek Solar LLC
712 MWWithdrawn / abandoned Leon, TXERCOT Dec 2021target 2025
Page 1 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)