United States βΊ Grid βΊ Interconnection queues
GAS Β· ERCOTBrownsville G
Brownsville G is a 871 MW gas request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2012 (completed)
- Withdrawn / abandonedAug 2018 (project stopped here)
- ConsentedJun 2015 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 16INR0005
- Grid region
- ERCOT (Texas)
- Developer
- Tenaska
- Connection point (POI)
- Tap 345kV 5966 Palmito - 80137 Stewart
- Technology
- Gas: 871 MW
- Total requested
- 871 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 12 July 2012
- Agreement signed
- 15 June 2015
- Proposed online date
- December 2020
- Withdrawn
- August 2018
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem