COAL Β· ERCOT

Tenaska Trailblazers

Tenaska Trailblazers is a 850 MW coal request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0003
Grid region
ERCOT (Texas)
Developer
Tenaska Trailblazers Partners, LLC
Technology
Coal: 850 MW
Total requested
850 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
19 February 2008
Proposed online date
June 2019

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem