GAS Β· ERCOTNavarro Energy Ctr. II
Navarro Energy Ctr. II is a 775 MW gas request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2007 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 10INR0032
- Grid region
- ERCOT (Texas)
- Developer
- Summit Navarro, LLC
- Technology
- Gas: 775 MW
- Total requested
- 775 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 11 December 2007
- Proposed online date
- December 2050
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem