United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTShell Windenergy - Briscoe
Shell Windenergy - Briscoe is a 2,940 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2007 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 10INR0024
- Grid region
- ERCOT (Texas)
- Developer
- Shell Windenergy, Inc. & Luminant
- Technology
- Wind: 2,940 MW
- Total requested
- 2,940 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 22 October 2007
- Proposed online date
- January 2013
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem