NUCLEAR Β· ERCOT

Comanche Peak 3 and 4

Comanche Peak 3 and 4 is a 3,200 MW nuclear request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0002
Grid region
ERCOT (Texas)
Developer
TXU Generation
Technology
Nuclear: 3,200 MW
Total requested
3,200 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
15 September 2006
Proposed online date
December 2021

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem