πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

GAS Β· ERCOT

Site C Brazos G

Site C Brazos G is a 800 MW gas request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
17INR0013
Grid region
ERCOT (Texas)
Developer
Brazos Elec Coop
Connection point (POI)
tap one 345kV Venus - 68090 Sam Switch ckt
Technology
Gas: 800 MW
Total requested
800 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
25 April 2014
Proposed online date
August 2021

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem