United States βΊ Grid βΊ Interconnection queues
BATTERY STORAGE Β· ERCOTCobisa-Greenville
Cobisa-Greenville is a 2,023 MW battery storage request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2002 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedDec 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 06INR0006
- Grid region
- ERCOT (Texas)
- Developer
- Cobisa
- Connection point (POI)
- FG_COBISA_G118.000
- Technology
- Other Storage: 2,023 MW
- Total requested
- 2,023 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 29 July 2002
- Agreement signed
- 1 December 2008
- Proposed online date
- August 2017
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem