NUCLEAR Β· ERCOT

Victoria City Nuclear

Victoria City Nuclear is a 3,200 MW nuclear request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
11INR0011
Grid region
ERCOT (Texas)
Developer
Exelon Generation Company, LLC
Technology
Nuclear: 3,200 MW
Total requested
3,200 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
7 November 2007
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in