United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 81

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 81 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J4174, Poinsett County
Battery storage
140 MWIn study Poinsett, ARMISO Oct 2025target 2030
Battery storage project AI1-186, Shenandoah County
Battery storage
140 MWIn study Shenandoah, VAPJM Sep 2022target 2027
Solar project 672, Rankin County
Solar
140 MWIn study Rankin, MSSoutheast Oct 2024target 2027
Solar + storage project GEN-2020-010, Woodward County
Solar + storage
140 MWIn study Woodward, OKSPP Apr 2020target 2027
Solar project J2983, Grant County
Solar
140 MWIn study Grant, ARMISO Sep 2022target 2025
Battery storage project AH2-083, Caroline County
Battery storage
140 MWIn study Caroline, VAPJM Jan 2022target 2027
Solar project J2972, Adams County
Solar
140 MWIn study Adams, ILMISO Sep 2022target 2026
Battery storage project AI1-181, Venango County
Battery storage
140 MWIn study Venango, PAPJM Sep 2022target 2027
Onshore wind project J3918, Champaign County
Onshore wind
138 MWIn study Champaign, ILMISO Feb 2025target 2028
Battery storage project J2657, White County
Battery storage
138 MWIn study White, INMISO Sep 2022target 2027
Demeter Storage 2
Solar + storage · Demeter Solar, LLC
138 MWIn study Caldwell, TXERCOT Oct 2024target 2029
Gas project ERAS-2025-035, Brown County
Gas
138 MWIn study Brown, SDSPP Oct 2025target 2029
Solar project LGE-GIS-2023-007, Hopkins County
Solar
138 MWIn study Hopkins, KYSoutheast Aug 2023target 2027
Sword Solar
Solar + storage · Hidalgo Solar LLC
137 MWIn study Starr, TXERCOT Mar 2024target 2029
Gas project 22
Gas
136 MWIn study FLSoutheast Aug 2018target 2019
Battery Storage
Battery storage
136 MWIn study Berkshire, MAISO-NE Apr 2024target 2028
Gas project GEN-2024-286, Le Flore County
Gas
136 MWIn study Le Flore, OKSPP Mar 2025target 2031
Turtle Rock Storage
Battery storage · Turtle Rock Energy Center, LLC
136 MWIn study Freestone, TXERCOT May 2024target 2028
Replacing 135.5 MW with 135.5 MW BESS; Blue Lake Units 1 2 4
Other
136 MWIn study Scott, MNMISO May 2024target 2027
Pulaski Energy Storage
Battery storage · Pulaski Energy Storage LLC
135 MWIn study Baltimore, MDPJM Feb 2025target 2025
Onshore wind project 2021-G6, Yavapai County
Onshore wind
135 MWIn study Yavapai, AZWest Jun 2021target 2025
Solar + storage project GEN-2023-063, Rogers County
Solar + storage
135 MWIn study Rogers, OKSPP Oct 2023target 2028
Solar project J1816, Cross County
Solar
135 MWIn study Cross, ARMISO Mar 2022target 2025
Solar project J3283, Grand Traverse County
Solar
135 MWIn study Grand Traverse, MIMISO Apr 2024target 2028
Solar + storage project J3082, Franklin Parish County
Solar + storage
135 MWIn study Franklin Parish, LAMISO Sep 2022target 2026
Solar project J2985, Chicot County
Solar
135 MWIn study Chicot, ARMISO Sep 2022target 2025
White Creek Solar
Solar · White Creek Solar, LLC
135 MWIn study Livingston, NYNYISO Nov 2018target 2028
Stonewall BESS
Solar + storage · Stonewall ESS, LLC
135 MWIn study Stonewall, TXERCOT Feb 2025target 2028
Surplus; J33/J734
Other
135 MWIn study Ford, ILMISO May 2023target 2026
Surplus; J734
Other
135 MWIn study Mclean, ILMISO Dec 2022target 2026
Fraser Energy Storage
Battery storage · EDF Renewables Development, Inc.
135 MWIn study Delaware, NYNYISO Aug 2024target 2029
SR Warthen
Solar
135 MWIn study Washington, GASoutheast Dec 2024target 2029
Solar + storage project J2648, Champaign County
Solar + storage
135 MWIn study Champaign, ILMISO Sep 2022target 2027
Solar project GEN-2022-007, Lyon County
Solar
135 MWIn study Lyon, KSSPP May 2022target 2028
Solar project J2287, Bolivar County
Solar
135 MWIn study Bolivar, MSMISO Sep 2021target 2024
Marathon BESS
Battery storage · Marathon Power
135 MWIn study Suffolk, NYNYISO Sep 2024target 2028
Onshore wind project J1842, Cross County
Onshore wind
135 MWIn study Cross, ARMISO Oct 2021target 2024
Battery storage project GEN-2023-SR7, Wayne County
Battery storage
135 MWIn study Wayne, NESPP Dec 20222024
Onshore wind project AI2-390, Mclean County
Onshore wind
134 MWIn study Mclean, ILPJM Mar 2023target 2027
Pham BESS
Battery storage · ASB1, LLC
133 MWIn study Anderson, TXERCOT Jun 2024target 2028
Solar project J2809, Iroquois County
Solar
133 MWIn study Iroquois, ILMISO Sep 2022target 2026
Halcon Storage
Battery storage · TX BESS A LLC
133 MWIn study Starr, TXERCOT May 2023target 2028
Double A Solar SLF
Solar + storage · Double A Solar, LLC
133 MWIn study Goliad, TXERCOT Jun 2024target 2027
Gas project J3936, Kenosha County
Gas
132 MWIn study Kenosha, WIMISO Feb 2025target 2027
Surplus; J1316
Gas
132 MWIn study Kenosha, WIMISO Jan 2025target 2026
Solar project J1918, Montcalm County
Solar
132 MWIn study Montcalm, MIMISO Aug 2021target 2026
Solar project J3724, Vigo County
Solar
132 MWIn study Vigo, INMISO Apr 2024target 2028
Wind + storage project 614, Twin Falls County
Wind + storage · Magic Valley Energy, LLC
132 MWPaused / redesign Twin Falls, IDWest Aug 2021target 2026
Gas project 118, Polk County
Gas
132 MWIn study Polk, FLSoutheast Apr 2025target 2026
Kodiak AGR1
Other · Hunt Energy Network, LLC
132 MWIn study Reeves, TXERCOT Feb 2024target 2027
Page 81 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)