United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Demeter Storage 2

Demeter Storage 2 is a 138 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Caldwell County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0523
Grid region
ERCOT (Texas)
Developer
Demeter Solar, LLC
Connection point (POI)
Tap 138kV 7224 LULING - 7216 Lockhart
Location
Caldwell County, Texas
Technology
Battery: 138 MW · Battery
Total requested
138 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
1 October 2024
Proposed online date
June 2029

Location

Marker shows the centre of Caldwell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Caldwell County