Metro BESS

Metro BESS is a 207 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Caldwell County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0478
Grid region
ERCOT (Texas)
Developer
Metro BESS LLC
Connection point (POI)
#9074 LYTTON5 345kv
Location
Caldwell County, Texas
Technology
Battery: 207 MW
Total requested
207 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
25 February 2025
Proposed online date
December 2030

Location

Marker shows the centre of Caldwell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Caldwell County